Update – Week of February 23, 2026

We wanted to provide a quick update on the work completed this week and the upcoming work planned for next week. 

Completed Works – Week of February 23rd, 2026

  • Continued installation of silt fence and tree protection fencing.
  • Began installation of the temporary haul road from the existing parking lot to the pile locations.
  • Began stockpiling granular material in the existing parking lot.
  • Completed soil sampling in the areas where material will be hauled off-site next week.

Week of March 2nd, 2026

  • Equipment on site will continue installing silt fence and tree protection fencing.
  • Soil sampling will continue in the areas where excavation is planned.
  • Stripping of topsoil will begin in the areas designated for the exfiltration manholes and bioswales (pending receipt of soil sampling results).
  • Continued hauling of granular material to the site. 

Schedule continuing until March 30, 2026

  • Receiving material to finalize building pads and to construct the exfiltration manholes and bioswales.

Clarifications

  • The construction path is temporary and will be removed as piling work is completed. Asphalt was never proposed.
  • No trees have been removed, nor are any planned to be removed as part of these works.