Update – Week of March 2, 2026

Completed Works – Week of March 2nd, 2026

  • Continued installation of silt fence and tree protection fencing.
  • Granular material stockpiling on site continued.
  • Finalized soil sampling in the areas where material will be hauled off-site.

Week of March 9th, 2026

  • Equipment on site will continue installing silt fence and tree protection fencing.
  • On-site granular material to be relocated to commence construction of piles

Schedule continuing until March 30, 2026

  • Stripping of topsoil will begin in the areas designated for the exfiltration manholes and bioswales (pending receipt of soil sampling results).
  • Receiving material to construct the exfiltration manholes and bioswales.

Clarifications

  • The construction path is temporary and will be removed as piling work is completed. Asphalt was never proposed.
  • No trees have been removed, nor are any planned to be removed as part of these works.
  • There has been no installation of light standards or hydro poles