Completed Works – Week of March 2nd, 2026
- Continued installation of silt fence and tree protection fencing.
- Granular material stockpiling on site continued.
- Finalized soil sampling in the areas where material will be hauled off-site.
Week of March 9th, 2026
- Equipment on site will continue installing silt fence and tree protection fencing.
- On-site granular material to be relocated to commence construction of piles
Schedule continuing until March 30, 2026
- Stripping of topsoil will begin in the areas designated for the exfiltration manholes and bioswales (pending receipt of soil sampling results).
- Receiving material to construct the exfiltration manholes and bioswales.
Clarifications
- The construction path is temporary and will be removed as piling work is completed. Asphalt was never proposed.
- No trees have been removed, nor are any planned to be removed as part of these works.
- There has been no installation of light standards or hydro poles