Update — Week of March 30, 2026

  • Similar to last week, work continued on site to complete the export of material from the fill piles to a designated off-site facility.
  • Crews also continued relocating stone on site to construct the test fill piles.
  • Additional soil testing was completed, with the City of Ottawa’s consultant present.
  • Several vibration monitors remain in place, providing continuous monitoring to ensure all construction activities stay within acceptable levels.
  • Next week, crews will continue hauling material from the test pile footprints to the designated facility, while construction of the test fill piles progresses.
  • In addition, crews will begin installing the ‘exfiltration manhole system’ and ‘bioswale system’.
  • We will continue to collaborate closely to ensure clear communication and timely updates, while maintaining full compliance with all required approvals and applicable regulations.